COSMOS 1.1 Iteration5 Features
Contents
COSMOS v1.1 iteration 5 plan
Schedule for Iteration 5
Design doc every enhancement
- if the enhancement is really small, put in at least a paragraph and a link to the use case for QA and documentation.
- if the enhancement is not small, the design doc needs to explain the change, anyone other than the assignee who is affected, how much work it is, any ramifications, and in general please avoid any changes to 3rd party materials other than removing a dependency on it. We have no guarantee that the change will be approved for COSMOS v1.1.
Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc)
Sizing legend:
- Low - takes 1-3 days
- Medium - takes a week
- High - takes more than a week
Status to be filled in by:
- Data Collection bugzilla status (Jimmy Mohsin)
- Data Visualization bugzilla status (Jimmy Mohsin)
- Resource Modeling bugzilla status (David Whiteman)
- Management Enablement bugzilla status (Jason Losh)
- RE/Build bugzilla status (Saurabh Dravid)
- QA bugzilla status (No owner)
- Doc bugzilla status (No owner)
- Legal & release review prep and status (Jason Losh)
The Status column can have one of these values:
- COMPLETE
- On track
- At risk
- Not containable
- Defer (no longer a priority for this iteration)
- Not started
Priority | Status | Project or subteam | Enhancement | Severity | Description | Blocked by (if applicable) | Owner | Sizing | Design Doc | Use Case |
---|---|---|---|---|---|---|---|---|---|---|
High | On track | Management Enablement | 273067 | Enhancement | Refactor op/installer as OSGi bundle | Ed Blackman | High | N/A | N/A | |
High | COMPLETE | Management Enablement | 274067 | Defect | Update targetResourceRef attribute in COSMOS SDD | Jason Losh | High | N/A | N/A | |
High | COMPLETE | Management Enablement | 275669 | Enhancement | Connect CLIAdapter to SDD Runtime Orchestrator | Jeff Hamm | High | |||
High | COMPLETE | Management Enablement | 275673 | Normal | Refactor the advisor bundle to move the CLI | Jeff Hamm | High | N/A | N/A | |
High | COMPLETE | Management Enablement | 275881 | Enhancement | Handler for Relational Database | Josh Hester | Medium | design | ||
High | COMPLETE | Management Enablement | 275883 | Enhancement | Handler for J2EE | Jeff Hamm | Medium | |||
High | COMPLETE | Management Enablement | 275670 | Enhancement | Handler for JRE | Josh Hester | Medium | |||
High | COMPLETE | Management Enablement | 275674 | Enhancement | Need to resolve translation strings | Josh Hester | Medium | |||
High | COMPLETE | Management Enablement | 275731 | Enhancement | Resource handler to check for installed products | Jeff Hamm | Medium | design | ||
High | Not started | Management Enablement | 275734 | Enhancement | Design a MDR for COSMOS Runtime | Jason Losh | High | |||
Low | COMPLETE | Management Enablement | 276507 | Defect | Fix COSMOS example | Jason Losh | Low | N/A | N/A | |
Medium | COMPLETE | Resource Modeling | 276993 | Defect | SML Validator Implementation does not support final standard | John Arwe | Medium | N/A | N/A | |
Medium | On track | Resource Modeling | 271062 | Defect | Handle feedback from RTx review (HP) | Mark Johnson | Medium | N/A | N/A | |