COSMOS 1.2 Release Plan
Overview
Please send comments about this plan to the cosmos-mgmt@eclipse.org project management mailing list.
This document lays out the feature and API set for the COSMOS releases.
This plan describes the deliverables, milestones, and plan items for the COSMOS project. Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved. Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.
Release Deliverables
The following release deliverables are provided:
- Runtime
- Tooling
- Source
- Examples
- Component Tests
- Data Collection Implementation
- Data Visualization Implementation
- Resource Modeling Implementation
- Management Enablement Implementation
- CMDBf Implementation
Release Milestones
This COSMOS 1.2 release is targeted for general availability on June 30th 2010. All deliverables will be available for download as soon as the release has been tested and validated in the target configurations. The project will follow one month iterations consisting of three weeks for development and one week for test. There will be a total of eight iterations broken out in the release schedule below.
Milestone | Duration | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Description | Comments | |
Iteration 1 | 1 Month | Nov-2-2009 | Nov-30-2009 | Enhancements | ||||
Development | Nov-2-2009 | Nov-23-2009 | Development & bug fixes | |||||
Testing | Nov-24-2008 | Nov-30-2009 | Validation Testing | |||||
Iteration 2 | 1 Month | Dec-1-2009 | Dec-24-2009 | Enhancements | ||||
Development | Dec-1-2009 | Dec-18-2009 | Development & bug fixes | |||||
Testing | Dec-21-2009 | Dec-24-2009 | Validation Testing | |||||
Iteration 3 | 1 Month | Jan-4-2010 | Jan-29-2010 | Enhancements | ||||
Development | Jan-4-2010 | Jan-22-2010 | Development & bug fixes | |||||
Testing | Jan-25-2010 | Jan-29-2010 | Validation Testing | |||||
Iteration 4 | 1 Month | Feb-1-2010 | Feb-26-2010 | Enhancements | ||||
Development | Feb-1-2010 | Feb-19-2010 | Development & bug fixes | |||||
Testing | Feb-22-2010 | Feb-26-2010 | Validation Testing | |||||
Iteration 5 | 1 Month | Mar-1-2010 | Mar-31-2010 | Milestone Driver | ||||
Development | Mar-1-2010 | Mar-19-2010 | Development & bug fixes | |||||
Testing | Mar-22-2010 | Mar-31-2010 | Validation Testing | |||||
Iteration 6 | 1 Month | Apr-1-2010 | Apr-30-2010 | Enhancements | ||||
Development | Apr-1-2010 | Apr-23-2010 | Development & bug fixes | |||||
Testing | Apr-26-2010 | Apr-30-2010 | Validation Testing | |||||
Iteration 7 | 1 Month | May-3-2010 | May-31-2010 | Enhancements | ||||
Development | May-3-2010 | May-24-2010 | Development & bug fixes | |||||
Testing | May-25-2010 | May-31-2010 | Validation Testing | |||||
Iteration 8 | 1 Month | Jun-1-2010 | Jun-25-2010 | Release Driver | ||||
Development | Jun-1-2010 | Jun-11-2010 | Development & bug fixes | |||||
Testing | Jun-14-2010 | Jun-25-2010 | Validation Testing | |||||
COSMOS 1.2 availability | 1 day | June-30-2010 | June-30-2010 | GA Release |
See 259011 for details on how those release review dates were calculated. They are tentative and may change.
Major deliverables
- Conversion of all SDD tools to JAXB
- SDD conformance level two implementation
- Eclipse plug-in for SDD editing
- Alignment with P2 for deploying non-OSGi specific applications
- SDD generator addition to create SDDs from MSI packages
Features
Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced. Plan items are allocated to the projects indicated above.