WTP 2012-12-13
Contents
WTP Development Status Meeting
Remember, any committer can add an agenda item. Typically, short announcements or news items go in the "Announcements" section at the beginning. Longer items or issues requiring discussion should go in the "Other business" section at end.
Announcements And Special Reports
WTP Calendar
(Weekly Google Calendar)
For Juno/Kepler overall dates, see the Simultaneous Release Calendar
Focus on Quality (Neil)
- Improve:
- Major or higher severity bugs by project (This week - 147, last week - 146)
- Targeted to Future (candidates for severity downgrade?) (Total - 86, last week - 86)
- Triage:
- Untargeted bugs and enhancements with patches attached over 7 days old (This week - 59, Last week - 60)
- Untargeted severity "Major" and higher bugs opened over 7 days ago (This week - 33, Last week - 35)
- Options:
- Target to a specific release or "future" if planning to fix but not in the next release
- Adjust severity as appropriate
WTP 3.4.2
3.4.2 Schedule
- 12/13 Weekly maintenance driver smoke and declare
- 12/20 No declare - Happy Holidays!
... Holiday Break ...
- 01/03 Regular M Build declare
...
- 2/22/2013 Juno SR2 GA
Bug Review
WTP 3.5: Kepler!
- Smoke Test Results
- Kepler planning - Top Level Plan
- Plan requirements....
- Platform Kepler release requirement document approved
3.5.0 Schedule
- 12/13 M4 Candidate build
- 12/21 Official Kepler 3.5.0 M4 availability - no declare
... Holiday Break ...
- 01/03 Regular M5 I Build declare
- 02/08 Official Kepler 3.5.0 M5 availability - no declare
...
- 06/26 Kepler GA
See "references" [1] for detailed explanation of what these dates mean.
Bug Review
Other business
- ICU4J Version changing (4.4.2 --> 50.1.0)
- WTP Datatools project is undergoing a termination review - Bug 396369
- Ongoing GIT discussion
- Discuss Git workflows, best practices, project standards(versioning) experiences etc...
- WTP Git Workflows
- Git education wiki page
- VJET Incubation
- git repos are setup - http://www.eclipse.org/projects/project.php?id=webtools.vjet - hudson build is being setup - https://hudson.eclipse.org/hudson/job/webtools-vjet-juno - currently blocked with build with tests not running - Q: Do you have build ready for distribution? ... There is an incubator download page for webtools - documentation is being ported over to eclipse.org... wiki.eclipse.org/VJET/* - type libraries are going through IP process. Type libraries are not checked in currently pending. - VJET talk 12/12/2012 - http://wiki.eclipse.org/Eclipse_Day_At_Googleplex_2012/Session_Abstracts#.7Blearnhowto:_.22tame_the_JavaScript_Monster_with_.23vjetjside.22.7D - VJET Eclipsecon paper - http://www.eclipsecon.org/2013/sessions/learnhowto-tame-javascript-monster-vjetjside
- Nitin: Proposal to simplify features in Kepler (specifically UI vs core features).
- Anything else?
References
- ↑ Our plan dates are on 'Friday' of the week. But, we produce and test the build on Thursday of the week, and ideally declare on Thursday. The dates in the Google Web Tools group calendar are for 'Thursdays' since that's a calendar for committers. We give ourselves the buffer to Friday, as our "public" date, that others can pick up our build, just in case a regression is found on Thursday and we have to respin and retest. [Technically, some might say, we still have till the following Tuesday or Wednesday for some "Simultaneous Release" due dates ... but it's hard to do much in that window, without disrupting everyone ... so we'll not use that buffer, except for the worst emergencies.]
- ↑ Hotbug Policy