WTP Development Status Meeting
Remember, any committer can add an agenda item. Typically, short announcements or news items go in the "Announcements" section at the beginning. Longer items or issues requiring discussion should go in the "Other business" section at end.
Announcements And Special Reports
WTP Calendar
(Weekly Google Calendar updated through June, 2012)
For Juno overall dates, see the Simultaneous Release Calendar
Focus on Quality (Neil)
- Improve:
- Major or higher severity bugs by project (This week - 157, last week - 156)
- Triage:
- Untargeted bugs and enhancements with patches attached over 7 days old (This week - 50, Last week - 45)
- Untargeted severity "Major" and higher bugs opened over 7 days ago (This week - 34, Last week - 31)
- Options:
- Target to a specific release or "future" if planning to fix but not in the next release
- Adjust severity as appropriate
WTP Moving to GIT!
- Problems with migrated content - recommend all teams request do-over with cvs2git.
- Team's should also request http Git push access
- Carl to give update on build progress
- Repositories will require Java 6 due to pack200 issue - see bug 386508
- Discuss Git Checklist
- Start playing with Git now! This is very useful
- Git education wiki page
WTP 3.4.1
- No build... Git migration in progress
3.4.1 Schedule
- 8/2 M Build (will be late - fingers crossed?)
- 8/9 M build
- 8/16 RC1 build (after this build, begin PMC-review ramp-down (+1 begins))
- 8/30 RC2 build (after this build, begin PMC-review ramp-down (+2 begins))
- 9/6 RC3 build (after this build, begin PMC-review ramp-down (+3 begins))
- 9/13 final M build (with one week of buffer following this week, quiet week, until 9/28 (re-spin would require +3))
- 9/28 Juno SR1 GA
Bug Review
WTP 3.5.0 Kepler!
- No build... Git migration in progress
- Start planning - top level document being created soon
3.5.0 Schedule
- 8/9 initial declare
- 8/17 WTP M1 declare
- 8/24 Official Kepler 3.5.0 M1 availability - no declare
See "references" [1] for detailed explanation of what these dates mean.
Bug Review
Other business
- All project leads should update project metadata (bugzilla targets, release info, Kepler?)
- Recent incubation activity -
- Anything else?
References
- ↑ Our plan dates are on 'Friday' of the week. But, we produce and test the build on Thursday of the week, and ideally declare on Thursday. The dates in the Google Web Tools group calendar are for 'Thursdays' since that's a calendar for committers. We give ourselves the buffer to Friday, as our "public" date, that others can pick up our build, just in case a regression is found on Thursday and we have to respin and retest. [Technically, some might say, we still have till the following Tuesday or Wednesday for some "Simultaneous Release" due dates ... but it's hard to do much in that window, without disrupting everyone ... so we'll not use that buffer, except for the worst emergencies.]
- ↑ Hotbug Policy