WTP 2011-01-13
Contents
WTP Development Status Meeting
Attendees
|
|
|
Note: feel free to correct any errors/omissions in above attendance record.
Remember, any committer can add an agenda item. Typically, short announcements or news items go in the "Announcements" section at the beginning. Longer items or issues requiring discussion should go in the "Other business" section at end.
Announcements And Special Reports
- Be sure to nominate your favorites for the Eclipse Awards
- Congratulations are in order for two successful reviews:
- JPA_Diagram_Editor_Project (see bug 333439 for mechanics to complete the move.
- Libra (or, ... the loooong name: Enterprise Tools for OSGi™ Service Platform)
WTP Calendar
(Weekly Google Calendar updated through June, 2011)
For Indigo/Helios overall dates, see a Simultaneous Release Calendar
WTP 3.2.3
- Ready to declare latest build?
- Bug Review
3.2.3 schedule
- 01/14 Declared M-build [contributed to Helios SR2 RC1 +2 due on 01/19]
- PMC +1 review from 01/14 to 01/28
- 01/21 Declared M-build
- 01/28 Declared M-build [contributed to Helios SR2 RC2 +2 due on 02/02]
- PMC +2 review from 01/28 to 02/04
- 02/04 Declared M-build [contributed to Helios SR2 RC3 +2 due on 02/09]
- PMC +3 review from 02/04 to 02/11
- 02/11 Final M-build [contributed to Helios SR2 RC4 +2 due on 02/16]
- 02/25 Official Release
- 01/14 Declared M-build [contributed to Helios SR2 RC1 +2 due on 01/19]
See "references" [2] for detailed explanation of what these dates mean.
WTP 3.3.0
- Ready to declare latest build?
Planning
- Standard Plans are done (right?)
- Any anticipated IP requests that do not yet have a CQ Open? (Deadline is coming up ... M5?).
Schedule
- M5 02/03 (for delivery to Indigo+2 on 02/08)
- M6 03/10 (for delivery to Indigo+2 on 03/15)
- M7 04/28 (for delivery to Indigo+2 on 05/03)
- RC1 05/12 (for delivery to Indigo+2 on 05/17)
- RC2 05/19 (for delivery to Indigo+2 on 05/24)
- RC3 05/26 (for delivery to Indigo+2 on 05/31)
- RC4 06/02 (for delivery to Indigo+2 on 06/07) [Final build]
- GA 06/22
Other business
- ?
References
- ↑ Hotbug Policy
- ↑ Our plan dates are on 'Friday' of the week. But, we produce and test the build on Thursday of the week, and ideally declare on Thursday. The dates in the Google Web Tools group calendar are for 'Thursdays' since that's a calendar for committers. We give ourselves the buffer to Friday, as our "public" date, that others can pick up our build, just in case a regression is found on Thursday and we have to respin and retest. [Technically, some might say, we still have till the following Tuesday or Wednesday for some "Simultaneous Release" due dates ... but it's hard to do much in that window, without disrupting everyone ... so we'll not use that buffer, except for the worst emergencies.]
Also, see
WTP 3.2.x maintenance release plan
WTP_3.2_Ramp_down_Plan_for_Helios
See also the WTP Meeting Archive-Reference Page.