Skip to main content

Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Swordfish Documentation: Sprint Plan

{{#eclipseproject:rt.swordfish}}

Swordfish Sprints for Galileo

Swordfish Sprint Schedule

Update 27.03.2009: Merged sprints 4 and 5:

  • Fr. 03.04: Sprint 3 Demo, Retrospective + Feature Estimates+ Planning for Toolsuite
  • Mo. 06.04: Sprint 4 Planung for Runtime
  • Tue. 07.04 until incl. Mi. 29.04: Sprint 4 development
  • 31.04 Sprint 4 Review, Retrospective + Feature Estimates + Panning for Toolsuite
  • Mo. 20.04: Checkpoint: All mandatory M7 requirements fulfilled?
  • Thu. 30.04: Sprint 4 Demo


Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project. The Features and Tasks for Each sprint can be accessed through the links below:

sprint1: 09.02.2009 – 05.03.2009

sprint2: 06.03.2009 – 18.03.2009 (M6)

sprint3: 19.03.2009 – 02.04.2009

Swordfish Sprint 3 Review, Retrospective and Planning day - Friday 03 April 2009.

sprint4: 06.04.2009 – 29.04.2009

Checkpoint for M7 requirements - Monday 20 April 2009.

Sprint 4 Review, Retrospective and Planning day - Thursday 30. April 2009

Sprint 5: 04.05.2009 – 19.05.2009 (RC1)

Sprint 5 Review, Retrospective and Planning Day - Wednesday 20. May 2009

Release: 21.05.2009 – 17.06.2009 (Endgame)




Swordfish Wiki Home

Back to the top