Swordfish/Ramp down Galileo
Contents
Build Schedule
- Offset: +3 (milestones 3 weeks after the platform milestones)
Date | Name | Swordfish Release | Ramp-Down |
---|---|---|---|
05/01/2009 | Galileo M4 + 3 | ||
10/02/2009 | Galileo M5 + 3 | ||
19/03/2009 | Galileo M6 + 3 | EclipseCon, Project Plan freeze | |
03/04/2009 | 0.8 | ||
06/05/2009 | Galileo M7 + 3 | ||
20/05/2009 | Galileo RC1 + 3 | API Freeze, Feature freeze | |
Every week from 27/05/2009 | Galileo RC2..5 + 3 | Bug fixing (P1+P2) only | |
24/06/2009 | Galileo GA | 0.9 |
Until M7+3
- Continuous integration: Automated continuous builds and integration tests. Contributors are encouraged to use the latest builds.
- New features can only be integrated if they are part of the agreed feature back log.
RC1+3: API and feature freeze
- RC1+3 will be the last build which will contain new feature until Galileo is released. After the date, no modification on API or features will be accepted.
RC2..5 builds: The end-game
- Only bug fixing (P1 and P2 bugs), testing, samples and tutorials