Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Modeling Project Ramp Down Policy/Europa
Ramp Down for Europa
This ramp down policy applies to those Modeling projects taking part in the Europa release of Eclipse projects. Currently, the following projects are included:
- Eclipse Modeling Framework (EMF), including EMF Query/Transaction/Validation: +1 week from platform
- Graphical Modeling Framework (GMF): +2 weeks from platform
- Model Development Tools (MDT), includes UML2, OCL, XSD, EODM, UML2 Tools: +2 weeks from platform
For reference, see the Europa Simultaneous Release, in particular the Milestones and Release Candidates. In the case of Modeling projects, the dates below represent the last (+2 week) project release dates. +1 week projects (e.g. EMF) are expected the prior week in accordance with the schedule above.
Note that while these staggered dates apply to early development milestones, as Release Candidates are produced the time in between should naturally decrease until the final 'simultaneous' release on June 29th.
Ramp Down Details
Typically the last week of a Milestone is for testing, and fixing only regressions and P1 or blocking defects. For M6, we plan to be functionally and API complete and the remaining Release Candidates are (only) for fixing bugs, or fixing release required items (such as version numbers, licensing, etc.). Up to this point, Committers are expected to follow the normal Eclipse development practices when committing code.
For M7/RC0 to RC1, we expect each component lead (or delegate) to review and verify their teams' bugs.
After RC1 is produced, the time for general functional improvements is long past. The following describes the types of bugs that would be appropriate:
- A regression
- A P1 or P2 bug, one that is blocking or critical, and some cases of major severities.
- Documentation and PII files are exceptions to the normal PMC required review, since there is little chance of that breaking anything, though it is still expected to be complete by M6, and remaining work to be only documentation fixes (that is, no refactoring of plugins, build changes, etc, without PMC review and approval).
- In addition to a bug meeting the above priority/severity conditions, there should be a simple, safe, well understood fix that is well isolated from effecting other components, that doesn't affect API or adopters, that has been well reviewed and well tested.
- As each Release Candidate passes, the criteria for weighing the benefit-to-risk ratio criteria gets higher and higher, and as such requires a larger number of PMC members to review. As it is the Modeling project's practice to have each Project Lead on the PMC, getting approval to required fixes through RC2 should involve minimal overhead.
- After RC1 (May 23rd for +1, May 25th for +2): At least 1 PMC member (typically, the Project Lead) must review and vote + using the Bugzilla flag feature (see below).
- After RC2 (May 30th for +1, June 5th for +2): Another Committer from the component or project and at least 1 PMC member must review and vote +1 after reviewing the bug for appropriateness and risk.
- After RC3 (June 13th for +1, June 14th for +2): Two additional Committers and at least 2 PMC members must review and vote +1 after reviewing the bug for appropriateness and risk.
- June 22: Do zip, update, site preparations
- June 29: Release
Bugzilla Usage for RC Fixes
Committers can signify their approval for submitting fixes as required after RC2 by simply indicating +1 in a comment.
Bugzilla has a flag feature that is to be used for obtaining PMC approval. Enter the email address of the PMC member you are requesting approval from and submit. The PMC member is notified via email and will change the flag from '?' to '+' or '-' as appropriate.