Attendees
- Linda Chan (Actuate)
- Brian "Fitz" Fitzpatrick (Red Hat)
- Hemant Kolwalkar (IBM)
- Brian Payton (IBM)
Minutes
- Builds have started for 1.8.1
- Linda attended the Eclipse Architecture Council meeting this month. Not much to report.
- Helios SR1 and Indigo builds are starting up
- BIRT is in E-Week's Top 25 Eclipse Projects. Congrats to Linda and the Actuate team!
- Hemant will send Brian P. an updated version of the SQL model/Query model
- Linda requested that any API changes for 1.8.1 be put out for review before being committed