Attendees
- Brian Fitzpatrick
- Emily Kapner
- John Graham
- Sheila Sholars
- Brian Payton
- Larry Dunnell
- Der Ping Chou
- Linda Chan
Regrets
- Hung Hsi
Agenda
- DTP 1.6.1 M1 was released August 14th!
- Many thanks to Loic, Xiaoying, Larry, and Sheila for guiding it to completion
- Next important date -- M2 is August 25, 2008
- After that, we'll be on the Ganymede SR1 release train as a +1 project. You can see those dates [[here].
- September 2, 2008 - RC1
- September 9, 2008 - RC2
- September 16, 2008 - RC3 (Final Release, available September 24, 2008)
- Thanks for dispositioning some of the 1.6.1 target milestone bugs to M2, 1.6.2, or Galileo. Four bugs still remain. See them [here].
- We are at 20+ bugs with no target milestone set that need to be dispositioned. Please keep at this list daily if at all possible. [Here's the query.]
- Sub-project status (from team leads)
- Open discussion
Minutes
- Will use the Monday (SH time) build as the M2 build, which means folks can check in fixes until Sunday afternoon
- Emily has worked with Xiaoying to update the documentation files & features to fix some of the 1.6.1 doc issues and is waiting for a build to verify that things are fixed