Attendees
- John Graham
- Sheila Sholars
- Brian Fitzpatrick
- Linda Chan
- Hung Hsi
- Brian Payton
Regrets
- Der-Ping Chou
Agenda
- DTP 1.5.1 was released on Thursday, 9/27
- 94 bugs resolved
- 34 builds
- 3 months of work (June 29 --> September 26)
- Last minute heart attack award goes to SQL Dev for bug 204632
- No meeting next week: Eclipse Summit Europe, M --> F
- Builds on a "best faith" effort during the week, depending on internet connection
- Builds for DTP 1.5.2 start today, 10/1, when bugs are resolved (as we did in 1.5.1)
- Review project plans
Minutes
- Announcements from John
- Team reviewed the project plans and agrees that they are acceptable.
- Update on EclipseCon: Talk submissions open now
Action Items
- (John): 1 or 2 sentence summary of plans for each project.