DTP Connectivity Project Committers Meeting Minutes: January 15, 2007

Back to DTP Connectivity Project Committers' Meeting Page

Minutes

  • Project goals/themes for Europa
    1. Elevate provisional API to platform status
      • Improve unit test coverage
      • Improve documentation
        • Ensure all API are documented
        • Add general documentation (e.g. best practices, examples, etc.)
      • Revise any API that are awkward or inadequate (based on extender feedback)
        • Database recognition extension
        • DSE content extension mechanism for SQL model elements
    2. Support adopter migration from WTP RDB to DTP
      • Ensure feature compatibility
      • Provide technical assistance
    3. Integrate CP framework into ODA runtime
    4. Improve "generic" feature set
      • Expand generic DDL generation support to include SPs, UDFs, etc.
    5. Document contributor process
      • Define defect prioritization
        1. Defects with patches attached
        2. Defects related to release goals
        3. Other defects as time allows
      • Define best practices for defect logging
  • Project schedule
    • Project plan must be submitted to PMC by Feb. 16.
    • DTP became part of Europa "train" as of M4 (Dec 21). Next milestone: M5, Feb. 16.
    • See Europa milestones for more details (note, DTP is a +1 dependency)
  • Platform versions
  • Europa requirements

Action Items

  • Team: Comment on project goals
  • Team: Input for project plan due by Jan 31. (feature requests, bug fixes, etc.)

Attendees

  • Rob Cernich
  • Brian Fitzpatrick
  • Larry Dunnel
  • Linda Chan