DSDP/TM/Committer Phone Meeting 28-Jun-2006
Meeting Title: | TM Committer Phone Meeting |
Date & Time: | Wednesday Jun 28, 2006 at 6.30am PDT / 8.30am CDT / 9.30am Toronto / 3.30pm Salzburg |
Dial-in: | Skype martin.oberhuber, ddykstal, david-k-mcknight, kushal_munir, mikey_yo |
Fixed-line fallback dial-in:
- International +1 314-655-1411
- North America +1 877-422-0035 (toll free)
- Passcode: 764918
Contents
Attendees
- IBM - Dave Dykstal, Dave McKnight, Kushal Munir, Michael Berger
- Wind River - Martin Oberhuber
Agenda
- Our top goals
- Grow the Communities - active users and adopters. Provide something useful, and help them adopt it (tutorial, docs, mailinglist help).
- Get the APIs Right -- We need to enable API discussions in public.
- Get our Processes in place.
- Latest News
- Thanks for handling the Project IP Log properly
- Nightly builds in place as cron job on build.eclipse.org
- dsdp.eclipse.org vserver is set up, ready to serve online docs
- Status wrt to the Project Plan
- Finishing up M3 - Jun 30 - Functional Complete
- Wizard replaceable - Kushal committed the change, some more bug fixes to come
- Builds of User doc, Extension point doc, Dstore doc - DaveD
- Unit tests - Mike?
- Have ported the Framework + Tests -- 50 classes in 3 plugins -- but problems running it, keep working on it.
- DaveM status? EFS status? Tom Hochstein help?
- Some EFS bugs fixed, but not yet quite mature enough.
- Want to deliver as a separate "optional" feature, similar to "Team Extras" feature; needs half a day to assemble automated build for this.
- Open major and critical bugs
- Automatic Update Site - Martin to look at after M3
- Manual test plans - Martin to start putting together something
- Testing - As sent on dsdp-tm-dev list
- Features to be deferred
- Examples as separate download - defer, together with experimental EFS download
- User actions, Import/Export -- will be needed by IBM clients; deliver as "Experimental" but not part of 1.0, in order to have more time for the IP review
- What about "external tools" integration?
- Anything missing we need to do?
- FTP: How to do remote copy & move? - Wait for Jakarta Commons
- Finishing up M3 - Jun 30 - Functional Complete
- Work ahead (while DaveD is on vacation)
- Overhaul docs to be in sync with current code
- Userdoc: not in bad shape - needs manual review and update
- ISV doc: structural changes,
- link fixup (where ISV doc references the Javadoc) -- package name changes, classname changes -- get some tool help (import into a web building tool once it is built completely -- e.g. Adobe GoLive)
- Mike could do a first pass (catalog things to be fixed), Kushal can do a second one after some more refactoring
- More unit tests; server infrastrucure for automated testing
- Kushal - More refactoring (until end of july -- to be finished before M4)
- Drive the community RSE API Discussion -- API bug entries -- DaveM
- Remove references to "IBM", "etools" and similar strings -- DaveM
- Build warnings, usage of Platform Internal packages / classes
- DaveD already removed "deprecated" stuff and tried to find alternatives to "internal" stuff
- Some areas might not be easy (or even impossible) to remove -- most of them show up as warnings in PDE (currently 600)
- "hygiene" changes -- make changes as we go along for now: fix build warnings when a file is edited anyway; everybody to use default warnings; have a separate task for remaining the rest after M4
- Drive RSE 2.0 Planning
- Want Requirements for 2.0 by the Release Review (1 week after M5, end of september)
- Shall we have another F2F meeting? - Probably helpful if architectural things are to be discussed
- CDT developer summit will be end of september
- DD F2F not yet scheduled
- Plans: All Experimental stuff; New protocols on connection side; F2F meeting probably in November?
- Incorporate Jakarta Commons Net (as soon as approved by EMO)
- Overhaul docs to be in sync with current code
- Free discussion -- feelings, comments, critics
Action Items
- Last Meeting Action Items
- DaveD - Doc build, presistency bugs
- DaveM - bug fixing, hygiene changes, drive API discussion
- Kushal - bug fixing, refactoring, doc review
- Mike - junit delivery, doc review
- Martin - document bugzilla process and markups on website
- Setup vserver for serving online docs
- Review bug assignments, priorities, target milestones
- Update Project Plan, manual test plan, update site
Next Meeting
- Open DSDP/TM/Phone Meeting 5-Jul-2006 at 9am PST
- DSDP/TM/Committer Phone Meeting 19-Jul-2006 at 9.30am Toronto
- Dave D on vacation Jul 1-15