Corona/Plan
< Corona
- Note
- Corona is still in its incubation phase.
Contents
Release 1.0.0
Schedule
0.7.0
Start Date: | 2008-06-15 | Stop Date: | 2008-07-11 | Status: | active |
Objectives
- Synchronize with Eclipse 3.4 Ganymede
0.8.0
Start Date: | 2008-07-14 | Stop Date: | 2008-08-15 | Status: | planned |
Objectives
- Adoption of P2
1.0.0GA
Start Date: | Stop Date: | Status: | planned |
Objectives
- Currency with Eclipse 3.4 Ganymede release
- Initial release of Corona
Ramp Down Policy
Corona is still an incubator project that has yet to reach its initial release.
Milestone Builds
New functionality will continue to be added to its frameworks up to its initial RC build.
Release Candidate Builds
After the first RC build, Corona's build cycle will be every 2 weeks. During this time only bug fixes will be allowed. No new functionality should be accepted into Corona's source repository.
For the final RC and GA builds, only P1 and P2 fixes will be accepted.