This documents related to 2019-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2019.
Simultaneous Release | ||
Preceded by SimRel-2019-06 |
2019-09 2019 |
Succeeded by SimRel-2019-12 |
Common information
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release schedule
Release | Date | Span | Due dates | Notes |
---|---|---|---|---|
2019-09 M1 | Friday, July 19, 2019 | 07/12 to 07/19 |
|
3 weeks from 2019-06 GA |
2019-09 M2 | Friday, August 9, 2019 | 08/02 to 08/9 | 3 weeks from M1 | |
2019-09 M3 | Friday, August 30, 2019 | 08/23 to 08/30 |
|
3 weeks from M2 |
2019-09 RC1 | Friday, September 6, 2019 | 08/30 to 09/06 |
|
1 week from M3 |
2019-09 RC2 | Friday, September 13, 2019 | 09/06 to 09/13 | 1 week from RC1 | |
Quiet period | 09/13 to 09/17 | No builds during "quiet period". It is assumed all code is done by the end of RC2. | ||
2019-09 GA | Wednesday, September 18, 2019 |
|
5 days from RC2 |