Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
COSMOSWeeklyProjectPlan
Week by Week Plan to get to the March Demo.
Resource Modeling; Steve Jerman
Status | Date | Milestone | Dependencies | Who |
Done | 2-Feb-2007 | SMLIF editor
(The code will be fully functional by Feb 2) |
None | Ali |
Done | 2-Feb-2007 | Import from SMLIF and export to SMLIF actions
(The code will be fully functional by Feb 2) |
None | David |
Done | 2-Feb-2007 | SML and SMLIF documents
(the instances are already available in CVS; Ali to make any required changes) |
None | Ali |
Done | April 2007 | Implement smlerr:output validator | None | David |
Done - more to be created | May 2007 | 172682 More tests to verify the SML validation implementation | None | David |
Done - to be validated | April 2007 | 178590 - Add SML definition of TPTP logging agents to data center example | This content will evolve as Data Collection and Reporying team will define requrirements | Valentina |
Open | April, May 2007 | https://bugs.eclipse.org/bugs/show_bug.cgi?id=180073 SML repository API for navigating an SML repository | The content will evolve as Data Visualization team will define API requirements | Valentina/ Ali |
Data Collection; Don Ebright
Status | Date | Milestone | Dependencies | Who |
Done | 1-Mar-2007 | Architecture and plan documents for June deliverables
|
None | Don |
Open | 30-Mar-2007 | Initial implementation of the COSMOS Data Collection framework
|
None | Don and Joel |
Open | 4-May-2007 | Framework enhancements
|
Data Collection Framework | Don and Joel |
Open | 4-May-2007 | Initial set of COSMOS Data Collection exemplary components
|
Data Collection Framework | DC team |
Open | 1-Jun-2007 | Additional exemplary components
|
Data Collection Framework | DC team |
Open | 1-Jun-2007 | Demonstrable COSMOS Data Collection component
|
Data Collection Framework and exemplary components | DC team |
Data Reporting; Craig Thomas
Status | Date | Milestone | Dependencies | Who |
Done | 26-Jan-2007 |
Topologies Report |
|
Sheldon |
Done | 2-Feb-2007 |
Nodes Report, Properties Report |
|
Sheldon |
Done | 9-Feb-2007 |
"top 10 report" of CBE data (https://bugs.eclipse.org/bugs/show_bug.cgi?id=172538) |
|
Sheldon |
Done | 9-Feb-2007 | Update setup instructions with current information Status as of 22-Feb-2007: complete. |
None | Sheldon |
Done | 16-Feb-2007 |
Status as of 15-Feb-2007: complete. |
|
Sheldon |
Open | 2-Mar-2007 |
Architecture and plan documents for June deliverables
|
none | Craig, Sheldon, Mark |
Open | 15-April-2007 | DV Framework and component design. See (https://bugs.eclipse.org/bugs/show_bug.cgi?id=180073) | none | Craig, Sheldon, Mark |