Resource Modeling; Steve Jerman

Status Date Milestone Dependencies Who
Done 2-Feb-2007 SMLIF editor

(The code will be fully functional by Feb 2)

None Ali
Done 2-Feb-2007 Import from SMLIF and export to SMLIF actions

(The code will be fully functional by Feb 2)

None David
Done 2-Feb-2007 SML and SMLIF documents

(the instances are already available in CVS; Ali to make any required changes)

None Ali
Done April 2007 Implement smlerr:output validator None David
Done - more to be created May 2007 172682 More tests to verify the SML validation implementation None David
Done - to be validated April 2007 178590 - Add SML definition of TPTP logging agents to data center example This content will evolve as Data Collection and Reporying team will define requrirements Valentina
Open April, May 2007 https://bugs.eclipse.org/bugs/show_bug.cgi?id=180073 SML repository API for navigating an SML repository The content will evolve as Data Visualization team will define API requirements Valentina/ Ali

Data Collection; Don Ebright

Status Date Milestone Dependencies Who
Done 1-Mar-2007 Architecture and plan documents for June deliverables
  • Comprehensive description of component architecture
  • Use cases for component adoption
  • Explanation of relationship to SML
  • Plan for June deliverables
None Don
Open 30-Mar-2007 Initial implementation of the COSMOS Data Collection framework
  • Definition of the component assembly framework SPI
  • Implementation of the component assembly framework
  • Implementation of binding and component context loading services deployable in an Equinox OSGi host
  • Definition of component APIs supporting all currently defined component types (data source, data sink, data filter, data transform)
  • Base classes for all currently defined component types
  • Component assembly schema
  • Automated build process for the data collection component
  • Documentation for building components upon the framework APIs
  • Automated unit test cases
None Don and Joel
Open 4-May-2007 Framework enhancements
  • Web container host
  • Framework manageability via WSDM and SML
Data Collection Framework Don and Joel
Open 4-May-2007 Initial set of COSMOS Data Collection exemplary components
  • Data collectors for the TPTP log agent and unix/Linux syslog
  • Data collector for TPTP statistical data agent
  • Data collector for WEF events
  • Data collector for Nagios
Data Collection Framework DC team
Open 1-Jun-2007 Additional exemplary components
  • Data collector for JMX events
  • Data collector for SNMP traps
Data Collection Framework DC team
Open 1-Jun-2007 Demonstrable COSMOS Data Collection component
  • Packaged demo that shows the implemented capabilities
  • Documentation to permit potential adopters to evaluate and adopt the frameworks
  • Other work as needed
Data Collection Framework and exemplary components DC team

Data Reporting; Craig Thomas

Status Date Milestone Dependencies Who
Done 26-Jan-2007

Topologies Report
Status as of 15-Feb-2007: complete.

  • Marius' work on getTopologies()
  • Valentina's work on SML-IF for demo ( Valentina : this work has been done by Ali )
  • Sheldon's review of this plan
Sheldon
Done 2-Feb-2007

Nodes Report, Properties Report
Status as of 15-Feb-2007: complete.

  • Marius' work on getNodeProperties(nodeId)
Sheldon
Done 9-Feb-2007

"top 10 report" of CBE data (https://bugs.eclipse.org/bugs/show_bug.cgi?id=172538)
Status as of 15-Feb-2007: complete.

  • Marius' API to provide a getLogData(node_id) or whatever the right API name is.
Sheldon
Done 9-Feb-2007 Update setup instructions with current information

Status as of 22-Feb-2007: complete.

None Sheldon
Done 16-Feb-2007

Status as of 15-Feb-2007: complete.

  • API to provide a getStatisticalData(node_id) or whatever the right API name is.
Sheldon
Open 2-Mar-2007

Architecture and plan documents for June deliverables

  • Comprehensive description of component architecture
  • Use cases for component adoption
  • Explanation of relationship to SML
  • Plan for June deliverables
none Craig, Sheldon, Mark
Open 15-April-2007 DV Framework and component design. See (https://bugs.eclipse.org/bugs/show_bug.cgi?id=180073) none Craig, Sheldon, Mark