Aperi Development Status Meeting 10/12/06
Aperi Wiki Home Aperi Meetings Aperi Development Meetings
Attendees:
Brocade (John Crandall), IBM (Craig Laverone, Todd Singleton, Brian Delaire, Ophelia Yip, Dave Wolfe, Brenda Haynes, Ted Slupesky, Chris King, Yolanda Martinez, Tom Guinane)
Minutes:
- Project Leader Notes (Ted)
- New date and time for this meeting
- After several options were discussed, it was agreed upon that Monday mornings at 9:00am Pacific works best for those on the call.
- Tom will post a notice to this affect on the aperi-dev mailing list and will follow up with a direct note to all of the committers to see if this time works for them as well.
- If OK with the majority of the team, the next Aperi Development meeting would be held October 23rd.
- John mentioned that he is not getting any aperi-dev notices. Tom will ask others if they are experiencing this same phenomenon as well (in the note on the meeting change).
- IBM contribution to Eclipse Legal Review status
- No change. The Eclipse team is in Esslingen Germany at the Eclipse Summit and not available this week.
- Khan at plugfest in Boulder:
- The logistics issues have been resolved.
- The Aperi scripted demo will be appearing as part of the Interop Demo at SNW in Orlando at the end of this month.
- New date and time for this meeting
- Release Lead Notes (Dave)
- Nothing this week
- Status on initial contribution items:
Task | Duration | Start | Finish |
---|---|---|---|
Eclipse legal Review | 27 days | Thu 9/7/06 | Thu 10/19/06 |
Load code into cvs at Eclipse | 1 day | Fri 10/20/06 | Fri 10/20/06 |
Contribution downloadable in Eclipse cvs | 0 days | Fri 10/20/06 | Fri 10/20/06 |
Build instructions - Eclipse cvs | 5 days | Mon 10/23/06 | Fri 10/27/06 |
- Updated Schedule - updates made in the schedule.
- Phase 2:
- Design
- Implementation
- Test
- Smoke Test Build Issues - Hans has added CMVC defect numbers. During the implementation phase we will review only the critical defects that are impeding the smoke tests. Need to discuss with Hans.
- ID
- Derby issues
- Action Items
Item | Owner | Target | Status |
---|---|---|---|
Third Party Dependency Questionnaire | Helen | 10/31/06 | Questionnaires submitted 9/6. - Eclipse has started the review. Checking with Eclipse for status and a possible target end date. |
Performance Issues | Hans | 10/12/06 | Hans to aggregate all the performance issues into one wiki page. |
Bug clean up | Dave | 10/31/06 | Figure out what to do with the remaining Aperi initial contribution bugs. Either fix or move to Bugzilla. |
- Other:
- Eclipse Summit
- Meeting day and time change
- addressed above as first topic
- Meeting time conflict on 10/12, 11/9, and 12/7.
- May become moot